Wednesday 18th & Thursday 19th June |
The rocket continues with the tiles, this is about 2400 affixed so far heading towards the valley area which will be formed using valley tiles and then close cutting into them.
This bit is a lot more time consuming than the normal tiling – a bit like the bonnets which will go on the corners.
The very last knockings of the timber work are being completed by the fox & me to form the correct slope to match the existing. This has proved very time consuming and any time we made on the main roof structure has now been lost. Still the last bit of roofing breathable felt and soffit to go on then its all over to rocket.
|